CPU
|
The cpu on which the job runs.
|
Schedule
|
The name of the schedule.
|
Job
|
The name of the job.
|
Job State
|
The state of the schedule or job. Job states are:
• | abend Job terminated with a non-zero exit code. |
• | abenp "abend" confirmation received, but job not completed. |
• | add Job is being submitted. |
• | done (MPE only) Job completed in an unknown state. |
• | error For an internetwork dependency, an error occurred while checking for the remote status. |
• | extrn For an internetwork dependency, unknown status. An error occurred, a rerun action was just performed on the EXTERNAL job, or the remote job or schedule does not exist. |
• | fail Unable to launch job. |
• | fence Job ’s priority is below the fence. |
• | hold Job awaiting dependency resolution. |
• | intro Job introduced for launching by the system. |
• | pend Job completed, awaiting confirmation. |
• | ready Job ready to launch, all dependencies resolved. |
• | sched Job’s at time has not arrived. |
• | succ Job completed with zero exit code. |
• | succp "succ" confirmation received, but job not completed. |
• | susp (MPE only) Job suspended by breakjob command. |
• | wait (X-agent jobs and MPE only) Job is being moved to ready. |
• | waitd (MPE only) Job is in the wait state, and is deferred. |
|
Priority
|
The schedule or job priority. A plus sign (+) preceding the priority means the job has been launched.
|
Estimated Start
|
Estimated job start time in HH:MM format. If the time is more than 24 hours in the future, the date is listed instead of the time.
|
Estimated Elapse
|
Estimated job run time based on logged statistics in MM:SS format.
|
Estimated End
|
Estimated job end time in HH:MM:SS format.
|
Start
|
Job start time in HH:MM format. If the time is more than 24 hours in the past, the date is listed instead of the time.
|
Elapse
|
Job run time in MM:SS format.
|
End
|
Job end time in HH:MM:SS format.
|
Job Number
|